CNCounty News

Supreme Court to decide Superfund case

Image of GettyImages-489009688.jpg

Key Takeaways

Atlantic Richfield Co. v. Christian is a complicated case raising three legal issues which the Supreme Court has agreed to decide. To summarize the case in one sentence, the owners of a Superfund site object to having to take remedial action not required by the Environment Protection Agency (EPA) to benefit landowners located within the boundaries of the site.  

The Anaconda Smelter, now owned by ARCO, processed copper ore from Butte for nearly 100 years before shutting down in 1980. That same year, Congress enacted the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) or Superfund law. The purpose of this law is to “foster the cleanup of sites contaminated by hazardous waste, and to protect human health and the environment.”

EPA required ARCO to pursue particular remedies. Landowners located within the boundaries of the site sought two additional remedies beyond what EPA required:  Removing the top two feet of soil from affected properties and installing permeable walls to remove arsenic from the groundwater.

ARCO argues that two provisions of CERCLA prevent the landowners from obtaining additional remedies in this case. ARCO also argues that CERCLA preempts state common-law claims for restoration beyond EPA-ordered remedies. The Supreme Court of Montana rejected all of ARCO’s arguments.

ARCO first claimed the landowners were “challenging” EPA’s remedial plan. The Superfund statute jurisdictionally bars courts from hearing “challenges.” According to the Supreme Court of Montana a “challenge must actively interfere with EPA’s work, as when the relief sought would stop, delay or change the work EPA is doing.” The court found no “challenge” in this case because “the Property Owners are not seeking to interfere with [EPA’s] work, nor are they seeking to stop, delay or change the work EPA is doing.”

ARCO also claimed the property owners are “Potentially Responsible Parties” (PRP), even though the EPA has never ordered them to pay for the cleanup. The Superfund statute prohibits PRPs from “conducting any remedial action that is inconsistent with EPA’s selected remedy without EPA’s consent.” The Montana Supreme Court noted the property owners have “never been treated as PRPs for any purpose — by either EPA or ARCO — during the entire 30-plus years since the Property Owners’ property was designated as being within the Superfund site.”

Finally, the Montana Supreme Court rejected the argument CERCLA preempts state common-law remediation claims pointing out that CERCLA has two savings clauses which “expressly contemplate the applicability of state law remedies.”

This case provides an interesting mixed bag for states and local governments. To the extent they own Superfund sites they may prefer that remedies be limited to what the EPA mandates. But to the extent others own Superfund sites, they may prefer they be remedied to a greater extent than what EPA requires.

Image of GettyImages-489009688.jpg

Attachments

Related News

Modern water cleaning facility at urban wastewater treatment plant. Purification process of removing undesirable chemicals, suspended solids and gases from contaminated liquid - Stock Photo
Advocacy

Senate begins reauthorization process for State Revolving Fund programs and other water infrastructure programs

On July 13, leaders of the U.S. Senate Environment and Public Works (EPW) Committee released the text of its Water Resources Development Act of 2026 (WRDA 2026). In addition to reauthorizing major projects through the U.S. Army of Corps of Engineers (Army Corps), the bipartisan legislation would reauthorize the Clean Water and Drinking Water State Revolving Fund (SRF) programs.

Image of WRDA_thumb.png
Advocacy

U.S. House Transportation & Infrastructure Committee advances 2026 Water Resources Development Act

On July 14, the U.S. House Transportation and Infrastructure Committee favorably reported H.R. 9497, the Water Resources Development Act of 2026 (WRDA) by a bipartisan 66-0 vote. The bill now awaits consideration by the full House of Representatives. The WRDA 2026 markup was originally scheduled for July 1 but was rescheduled to July 14 due to changes to the House calendar.

836124870
Advocacy

FERC orders regional grid operators to reform rules for large load grid connections

FERC orders regional grid operators to reform rules for large load grid connections